Public evidence brief · Churchill River desk · Newfoundland and Labrador

Keep the power here. Use it on loads that live here.

Newfoundland and Labrador generates about 43 of green electricity a year and sends most of it across the Québec border. The Churchill Falls / Gull Island , signed 17 August 2026, is a , not binding . The House endorsed that framework 21–18 on 17 September. Binding paper is still ahead. The industrial question is whether this province keeps is used here: mines and Labrador industry first. is not the opener. It lives on a separate page.

Prepared by Open People · St. John's, NL · Updated 2026-09-22 · Public briefing · DCIA framework, not PPAs · Open People is not a party to the agreement.

Last verified public documents onlyUNKNOWN labelled

Gates on the Churchill Falls framework, with today marked17 AugFramework signed17 SepHouse endorsed 21–185 OctQuébec votes31 DecBinding target31 MarFramework term ends

01 — The situation

One paragraph.

Newfoundland and Labrador owns one of the cleanest large power systems in North America. Churchill Falls alone is 5,428 . For decades it has been sold at a small fraction of what firm, carbon-free power commands today. In May 2026 the found the not in the long-term public interest as written. It cited limited rights to use the power in-province. On 17 August NL Hydro, Hydro-Québec and CF(L)Co signed the DCIA, announced with Ottawa in St. John's. It promises more in public framing, a higher reported export price, a Labrador West line and a wind study. It is a framework, not binding PPAs. The House endorsed it 21–18 on 17 September, with no referendum. That vote does not create contracts. Binding agreements are targeted around 31 December 2026. The framework can run to 31 March 2027. Québec votes 5 October. The province's stated industrial use is critical minerals. Mining matters, and it is first. Compute is optionality: not confirmed as reserved megawatts, price, queue or policy preference.

02 — The asset

What the province actually holds.

Megawatts drawn by how hard the number is. Solid is published. Outlined is announcement language. Hatched is preliminary. Dashed is not published.

Megawatts: published, announced, preliminary, not publishedProportional bars for Churchill Falls capacity, NL Hydro's current Labrador allocation, mining load, the public retain framing, Gull Island, upgrades, the wind study, and the unpublished industrial queue.Churchill Falls, existing plant5,428 MWNL Hydro's Labrador allocation today~525 MWof which sold to IOC and Tacora~312 MWPublic retain framing, CF + Gull Islandup to 2,350 MWGull Island, new plant2,250–2,700 MWChurchill Falls upgrades~1,275 MW by 2042Labrador wind, feasibility study2,000 MW study · 400 MW to NL if builtSigned industrial queue for retained powerNOT PUBLISHED
  • Published or in a regulatory document
  • Announcement language (Government of NL release)
  • Preliminary range or study, subject to studies
  • Not published
Churchill Falls, existing plant
Rated capacity of the existing plant (CER provincial profile). CF(L)Co: NL Hydro 65.8%, Hydro-Québec 34.2%.
NL Hydro's Labrador allocation today
About 525 MW allocated to NL Hydro from Churchill Falls to energize Labrador (CBC, Jan 2025); Annex B shows 525 MW existing-CF for NLH in 2027. More →
of which sold to IOC and Tacora
Mining load on the two Labrador West lines (CBC report of NL Hydro officials). Press cite, not a PUB order. More →
Public retain framing, CF + Gull Island
Gov NL 17 Aug 2026 announcement language. Not a signed industrial allocation, not a queue. More →
Gull Island, new plant
Schedule A: approximately 2,250 or 2,700 MW depending on final configuration, subject to studies. First power pencilled 2036. More →
Churchill Falls upgrades
Schedule A §1: about +23.5% across 11 units. Annex B ramp is preliminary. More →
Labrador wind, feasibility study
Schedule B §7: NLH-led study after Definitive Agreements; owner SPE unnamed; NLH 400 MW from 2039 in Annex B if built. More →
Signed industrial queue for retained power
No year-by-year meter of who gets retained megawatts is public. A headline number is not a schedule. More →

The province generated 44.3 TWh in 2023, and 43.1 TWh of it was renewable: 97.4%. It is hydro-dominated, dispatchable, and concentrated at a handful of interconnection points. For scale, 1,000 MW running all year is about 8.76 TWh. This is a large resource and a finite one. It should be allocated deliberately, not treated as limitless.

03 — The value gap

The export price is rising. The value-added still leaves the province.

Seven price families on one axis, each on its own row, labelled and not merged. Every rung carries its source. The one that would matter for a new Labrador load is blank.

The price ladderCents per kilowatt-hour on one axis, with each price family on its own row: heritage export, the rejected 2024 MOU, the reported new Hydro-Québec export path, published Labrador tariffs, the Island grid, Québec's proposed data-centre rate, and the signed industrial rate for retained power, which is not published.0¢2¢4¢6¢8¢10¢12¢14¢16¢18¢Heritage export0.2¢Rejected 2024 MOU3.8¢16.7¢Reported new HQ export path1.8¢6¢7.4¢11.5¢Published Labrador tariffs3.154¢Island grid (not Labrador)4.428¢15.587¢Québec data-centre rate (proposed)13¢Signed industrial ¢ for retained powernot publisheddifferent measurements · labelled, not merged
Heritage export
1969 renewal, two mills. Export price under a specific contract (2016–2041). Not a rate anyone here can buy at. Card →
Rejected 2024 MOU
MOU front block, 2025–2041. IRC levelized cost, 2024 dollars. The MOU expired 30 April 2026. Card →
Rejected 2024 MOU
MOU back block, 2042–2075. IRC levelized cost, 2024 dollars. Shows why the MOU 'average' hid a steep back end. Card →
Reported new HQ export path
Starts 2027 (reported). Starting price on the media graph, per NL Hydro. Not the fifty-year average. Card →
Reported new HQ export path
HQ release framing. Hydro-Québec's own 17 Aug release: “competitive rate of 6¢/kWh”. Its framing, not a schedule.
Reported new HQ export path
50-year average (reported). Canadian Press, corrected: averaging 7.4¢ over the next fifty years. Not the 2027 start. Card →
Reported new HQ export path
By 2041 (reported). NL Hydro description via CBC / Radio-Canada: rising about 14% a year to 11.5¢ by 2041. Card →
Published Labrador tariffs
Rate 1.1L domestic. Labrador Interconnected household energy, July 2026 schedule, plus a monthly customer charge. Card →
Island grid (not Labrador)
Island Industrial base (+ riders). IND-1 base energy before the 1.987¢ and 0.007¢ riders and demand charges. Island grid only. Card →
Island grid (not Labrador)
Island domestic first block. Hydro's current-rates page for Island Interconnected, L'Anse au Loup and isolated diesel. Not Labrador.
Québec data-centre rate (proposed)
HQ proposed data-centre rate. Filed with the Régie 19 Feb 2026 for data centres of 5 MW and up; decision expected around year-end.
Signed industrial ¢ for retained power
New Labrador industrial ¢ under the DCIA. No public, locked cent rate for retained Churchill / Gull Island megawatts. This desk does not invent one. Card →
LAB-IND-1
Published Labrador tariffs
The mine rate is demand charges plus a monthly formula, RFIRM = {(ED × RD) + (EM × RM)} / ETOTAL. It is not one cent and is not drawn as a rung. Card →

Each row measures something different. A starting price, a fifty-year average and a household tariff cannot be subtracted from one another. The desk labels them and refuses to merge them. Source for each rung is under its number.

Heritage

Heritage export (1969 renewal)

Structure

Rejected 2024 MOU path (IRC)

Reported

Reported HQ ¢ path (not a locked PPA)

Reported

HQ proposed data-centre rate

Under the 1969-lineage contract, Churchill Falls export power is priced at two , 0.2 , until 2041. That is an export price under a specific contract. It is not a rate anyone here can buy power at today.

The rejected 2024 MOU averaged about 5.9¢/kWh in 2024 dollars. The Independent Review took that average apart: about 3.8¢ from 2025 to 2041, then about 16.7¢ from 2042 to 2075. That path is history. NL Hydro has said Hydro-Québec will pay 1.8¢/kWh from 2027, rising about 14% a year to 11.5¢ by 2041. That is a reported path, not a signed contract price.

In February 2026 Hydro-Québec proposed a dedicated data-centre rate of 13¢/kWh for loads of 5 MW and up. It still expects takers. Québec is rationing and repricing exactly the hydro-seeking compute demand Labrador could serve. Near-term, this province would still sell the underlying power at a fraction of that.

The number that would matter for a new Labrador mine, or any new load, is the signed industrial cent for retained power. It is not published. We do not invent it.

Language discipline

The 0.2¢ figure is an export price under a specific contract. We never present it as a rate available to any customer today. Island retail sits on a different grid and a different tariff. This brief is a value-retention argument, not a grievance argument.

04 — The window

Why this is still a 2026 decision, not a finished deal.

The are the skeleton for contracts that do not yet exist. Each row below is a tracker entry with its own sources. Dates on the gate clock carry their status.

  1. Dec 2024

    Province and Hydro-Québec announce an MOU

    The province and Hydro-Québec announced a memorandum to replace the Churchill Falls terms and enable expansions, framed as a 2025–2075 arrangement. It expired 30 April 2026.

  2. 19 May 2026

    Independent Churchill River Review reports

    The Review found the MOU, as configured, not in the overall best long-term interest of the province. It flagged limits on using the power for in-province development, transmission access, pricing and governance.

  3. 2026

    Cooperation paper signed

    NL Hydro, Hydro-Québec, and CF(L)Co signed a cooperation paper in August. It is a framework for writing later contracts — not the contracts that lock the power.

  4. 2026

    House said yes 21–18

    The House said yes 21–18 after a special sitting, with no referendum. That is a political yes. It does not write power-purchase contracts.

  5. 18 Sep 2026

    Back to the House — but no promised vote

    The Premier says the deal comes back to the House before the binding contracts are signed. He has not said MHAs will get a vote. The next decision point may have no vote attached.

  6. 2026

    Québec votes 5 October

    The next public political gate is the Québec election. It is not an NL door you can walk through. The party that signed the paper is running third in the polls, and the front-runner has said it does not plan to tear the deal up — but it wants time to study it.

  7. /2026 / 2027

    Binding contracts still unsigned

    The parties say they want the real contracts around year-end. The framework clock can run into March 2027 unless they replace or extend it. While it runs, Hydro-Québec holds exclusive rights on Gull Island.

Public framing on announcement day: the province retains up to 2,350 MW from Churchill Falls and , plus 400 MW from Labrador wind if built. Not binding PPAs. Compute is still not named as a reserved use. On announcement day the mines minister named critical minerals. He did not name AI.

The corridor the mines need

The Review recommended new transmission from Churchill Falls to Labrador West specifically to enable energy-intensive industry. The August framework attaches money to that line. What is still missing is a public allocation: year, megawatts, place, price and line. Mines first, then other industrial load, including compute if the province writes it.

The corridor the mines needSchematic, not a map. Churchill Falls at the centre. Two existing 230 kV lines run west to Labrador West and are at their operational limit. A proposed 735 kV line with about 1,500 MW of transfer is funded but has no in-service date. Export lines run to Québec. Happy Valley–Goose Bay and the Churchill Falls townsite also sit on the system.2 × 230 kV · existingat operational limit735 kV proposed · ~1,500 MW · funded · in-service date not published735 kV export · ~90% of output flows to QuébecChurchill Falls5,428MWtownsite on the systemLabrador WestIOC · Tacora~312 MWLabrador City · Wabushmining firstQuébecHydro-QuébecHappy Valley–Goose Bay
  • — proposed 735 kV transfer limit, a planning figure
  • — on the two 230 kV lines today

Schematic only. Line lengths and positions carry no geographic meaning. Export share from the CER provincial profile. Corridor status from NL Hydro's Labrador West study page.

The mining corridor from Churchill Falls to Labrador West is already tight. The August announcement attaches money to a new line. Engineering and permits are under way this fall. Nobody has published when it switches on.

Still open in the text

01 · Recall

A consultant told the House a three-year notice recall could let the province keep more power at home. That is testimony. It is not confirmed in signed contract text.

02 · Innu Nation issues still open
Open

wrote MHAs on 17 September urging a no vote, and says the paper cuts its benefits by more than half. On 21 September the Grand Chief said the Innu are ready to meet. No meeting is scheduled. They were never invited to the table. Partnership, royalty and Gull Island tariff path remain open.

03 · Federal assessment

has not received proponent confirmation that 2026 Gull Island matches the 2012 review. The 2026 plant as described is larger than the roughly 2,000 MW studied then.

04 · Wind company not named
UNKNOWN

The wind company, an , is unnamed and at NL Hydro's sole discretion. We do not invent the name, a dollar figure or a federal share.

05 — Neighbouring grids (context)

Demand has repriced power elsewhere. That is not a Labrador reservation.

Neighbouring-grid facts that used to open this brief now live on the compute page, a separate page. They are context for leftover firm hydro, not a campus pitch, and not a named industrial class in the Material Terms.

Other provinces are rationing large new computing loads. That is context for leftover hydro — not a Labrador booking. Newfoundland and Labrador has no policy, no tariff, no allocation process and no project.

“Nobody builds AI infrastructure somewhere like Labrador”

Remote, cold and hydro-rich is the profile of the current build-out. Stargate Norway put a hydro-powered campus in Narvik, above the Arctic Circle. Meta has run a hydro-powered campus in Luleå, Sweden, since 2013. Google is expanding in Hamina, Finland. Training is latency-insensitive, so it goes to the power; inference stays near cities. Cold helps. Power decides.

Ottawa is already paying for this

Canada's Sovereign AI Compute Strategy seeks Canadian-owned, Canadian-controlled projects with Indigenous participation. A Labrador consortium of Crown power, Innu equity, an NL developer and Canadian anchor demand fits that description. The first intake closed in 2026. We found no Newfoundland and Labrador entry in the public record, because there was no NL project to enter.

06 — The ask

Five things, none of which cost money.

The province is not being asked to spend, build or subsidise. It is being asked to write five instruments into the architecture of the binding agreements, or the provincial framework beside them, before those agreements lock. House endorsement is not that lock. Year-end 2026 is the public target. The framework can run to 31 March 2027.

Open People ask · not a government figure

  1. 01A named block. A scheduled allocation of Labrador capacity eligible for industrial load, including compute, drawn from the publicly framed retain from Churchill Falls and Gull Island (section 02), plus wind if built. No firm megawatts, price or queue for Labrador compute is confirmed. An illustrative first tranche of 100–150 MW, as new generation phases in, is our ask. It is not a government figure.
  2. 02A transparent tariff. A published firm industrial rate, indicatively in the 4–6¢/kWh range, plus full network-addition cost causation. High enough to be unimpeachable after Muskrat Falls. Low enough to beat the data-centre rate Québec has proposed (section 05). The band is ours, not a posted rate.
  3. 03Allocation criteria that keep the value home. Score for NL majority ownership, Indigenous equity participation, creditworthy offtake, local employment and balance-sheet substance. Criteria, not a ban, are the durable answer to the Great North Data experience.
  4. 04An infrastructure audit. Direct NL Hydro to publish Labrador dark-fibre capacity and recall-block headroom, and commission a diverse-route fibre feasibility study. Co-fundable with federal connectivity programs.
  5. 05A federal handshake. A joint NL–Canada expression of interest under the Sovereign AI Compute Strategy, so the next intake window opens with a Labrador consortium already on file.

Every megawatt and cent in this block is an Open People ask. None is a published rate, a reserved block or a government figure.

Item 1 belongs in the binding agreements' architecture or their enabling provincial framework. Items 2 through 5 are ordinary policy instruments the province can move before those agreements lock.

The cost of doing nothing

  • 01The retained block defaults to mining and re-export. Public framing gives the province optionality on the retained block, plus wind if built. If other industrial uses, including compute, are not named as eligible, that optionality is spent on other files. Lawfully, and without a second chance inside this architecture.
  • 02The federal build-out passes the province by. Every subsidised megawatt lands where a project was ready. The first intake already closed without an NL entry that we can find.
  • 03Labrador's industrial story stays minerals-only. Mining is vital. It is also cyclical, and it employs at the mine, not at the grid.
  • 042041 arrives with no domestic alternative. The province's leverage in any future negotiation is a credible in-province use for the power: mines, towns, other industry, and compute if written eligible. The absence of that leverage is why 1969 happened.

If nobody writes anything else, the paper already decides.

The Material Terms describe what happens to retained power that is not used at home. It has a buyer. Leftover megawatts do not sit still by magic.

The default path for unused retained powerRetained power either serves domestic load in Newfoundland and Labrador, or, if unused, flows to Hydro-Québec under Section 4 options: synthetic export up to 280 MW, CHPE-equivalent up to 240 MW, NECEC-equivalent up to 200 MW, each on three years' notice, or unplanned unused energy at 95 percent of the PPA price with no notice, which Hydro-Québec must buy.Retained powerup to 2,350 MW · framingused here · “domestic load”not used · §4 optionsMines · towns · Labrador industrydefinition of “domestic load”: not publishedHydro-Québec buys italready written in the Material TermsSynthetic exportup to 280 MW · 3-yr noticeCHPE-equivalentup to 240 MW · 3-yr noticeNECEC-equivalentup to 200 MW · 3-yr noticeDiscounted PPA price95% of PPA · no notice · HQ must buy

Framework, not executed. These are Material Terms for later contracts. The point is that the west branch is already written and the home branch is not. Tracker row →

If NL does not use retained power at home, the paper already names ways Hydro-Québec can buy it — including a discounted default if there is no three-year notice. Leftover megawatts do not sit still by magic. What means in words a voter can check is still not written.

07 — Who builds it

A consortium, not a champion.

The structure that works, demonstrated at Narvik and consistent with the Review's governance critique, puts each risk with the party built to carry it. It is politically viable after Muskrat Falls because no single champion holds it.

Power and site
Crown utility: capacity allocation, brownfield land at the point of generation, transmission.
Indigenous equity
Innu Nation and its development entities: ownership from day one, not consultation at the end. The structure federal programs explicitly reward.
Development
An NL-based developer entity that assembles the coalition and carries the project.
Catalyst
Where Open People sits today. A public campaign for in-province use. Open People is not a DCIA party, an offtake seat or a demand seat, and does not assemble bankable offtake. A catalyst role, not a deal seat.
Software layer
Where Open People would sit if partners build. The sovereignty gateway, guardrails and model hosting that make in-province compute usable by buyers who cannot send data offshore.
Capital
Infrastructure investors and federal programs, following the power allocation, never preceding it.

Capital does not create power; power attracts capital. Québec, British Columbia, Ontario and Alberta have each just demonstrated which direction that queue runs.

08 — Honest constraints

What is genuinely hard about this.

A case built on cheerleading will fail in this province, and it should. Five constraints are real. None is a reason to leave the block unwritten, because a block that is never reserved is a permanent decision in favour of exporting raw electrons.

Fibre is the weakest link

Labrador's terrestrial backbone is essentially a single route, built in 2012. Region-wide outages from single events are on record. Hyperscale campuses want multiple physically diverse paths. Labrador has approximately one.

The workforce is already spoken for

The Churchill expansion program will itself absorb the province's construction trades at camp premiums. Muskrat Falls remains the controlling cost precedent for remote Labrador construction.

Nothing large proceeds without Innu consent, nor should it

Open

Ratification of any Innu Nation partnership on Gull Island remains unresolved. Innu Nation asked MHAs not to vote and says its benefits were cut by more than half. The Premier says he looks forward to sitting down; as of 21 September nothing is scheduled. That is a start, not consent, and not a partnership structure.

The Great North Data precedent

The province's one prior data-centre experience was a Labrador crypto operator that went bankrupt in 2019 owing money to the utility and public agencies. Municipal scepticism toward container mining is earned.

AI demand could correct

Lease cancellations in 2025 and a credible sceptic corpus warn of overbuild. If capex contracts later this decade, marginal sites die first.

09 — Who we are

Open People.

Open People is a Newfoundland and Labrador AI company developing sovereign, self-hosted computing: software built to run without resupply, on infrastructure its users actually control. Our role in this campaign is deliberately narrow: constituent and catalyst. We make the public case for keeping firm power in-province. We are not a DCIA party, an offtake seat or a demand seat. We are not asking to own the steel.

Tom Lane

Founder, Open People · St. John's, NL

Tom Lane is an entrepreneur based in St. John's. He is the founder of Open People and co-founder and owner of snōw white laundry, a seasonal restaurant on Water Street that opened in 2026. He took that project from lease negotiation through design, permitting and construction, acting as his own project manager with a local general contractor, and built its operating stack himself: supplier price intelligence, demand forecasting, financial automation and a custom staff platform.

It is a small building with a large point behind it. A regulated, multi-permit, multi-trade physical build on a compressed schedule is the same job shape as a first small compute node: site control, power and mechanical, inspectors, trades, and a licence gate at the end. He runs a 70-seat restaurant with the instrumentation of a data centre. This campaign is that continuity, applied to a bigger load.

10 — Falsifiability

What we have not proven.

This document is meant to be argued with. The following are open questions, not settled claims, and we say so in every room.

  • 01That the province will allocate firm Labrador power to compute over mining. Critical minerals are named first. Compute has to earn peer status on the merits. No firm megawatts, price, queue or policy preference for Labrador compute is confirmed.
  • 02That fibre economics support a training cluster at hyperscale path diversity. A first node likely fits. Hyperscale is unproven until the route studies exist.
  • 03That public-sector demand alone is large enough to bank a facility. It almost certainly needs commercial and federal co-funding alongside.
  • 04That binding definitive agreements will be signed on the announced timeline, or that they will free near-term megawatts for a compute node. House endorsement of the framework is not that signature, and the Premier has not promised a vote on the final text.
  • 05That a single industrial cent exists for Labrador mines. The current Labrador industrial schedule is a formula, demand charges plus a monthly energy mix. We do not flatten it, and we do not quote the 2015 schedule as current.
  • 06The reconciliation between the public retain figure and other published splits of the existing plant. Public releases also give Gull Island as a range. We do not pick a number.
  • 07That a three-year notice recall, as described to the House, appears in signed contract text.
  • 08That 2026 Gull Island matches the 2012 Lower Churchill federal review scope. IAAC has not received that proponent confirmation.
  • 09The name of the wind company. The special-purpose entity is unnamed in the public paper and the federal equity share is not in the Material Terms we read. We do not invent either.

Standing rule

Every figure on this page is bound to a public primary or reported source, and shows it when tapped. Where a number is an estimate, a range or an illustration, it is labelled as one. Where the public text does not say, we write UNKNOWN. If something here is wrong, we want to know. Corrections change the document.

11 — Sources

Where the numbers come from.

Every source below is in the desk registry and re-checked on the verified date at the top of the page. The same registry feeds the tracker, the ladder and the megawatt bars, so a number here and a number there are the same object.

Press

Named in prose only, not in the registry

  • International Energy Agency, Energy and AI (2025): global data-centre demand projection.
  • Innovation, Science and Economic Development Canada: Canadian Sovereign AI Compute Strategy programme materials.
  • Nscale and Aker: Stargate Norway announcements, August 2025.
  • CBC and Canadian Press, 2019: reported cumulative Churchill Falls profit split.
  • Newfoundland Power rate book: general-service energy charge ballpark.
  • CBC and provincial media: Great North Data bankruptcy (2019); Gull Island blockade (July 2025).

Figures from these appear only inside technical layers with a caveat, never on an instrument.

Prepared independently. All figures as publicly reported. A full claim-by-claim evidence table with confidence ratings sits behind this page and is available on request.

The power has to be allocatable here before anything else can happen.

If you want firm power kept in Newfoundland and Labrador, for mines, towns and other industry, with compute as a named use rather than a forgotten leftover, there is a public path this month.

Open People · St. John's, Newfoundland and Labrador
Briefing updated 2026-09-22 · Constituent and catalyst voice · not a DCIA party